Amid
Complaints of
$265M UN
Repair
Overrun, $147M
More, No DC5?
By
Matthew
Russell Lee,
Exclusive
UNITED
NATIONS,
March 12,
update March
13 -- With the
UN Security
Council full
of foreign
minister on
Monday, some
expressed
surprise at
the stage of
the
Capital Master
Plan
reconstruction
of the UN, and
the cost
overruns
under
Secretary
General Ban
Ki-moon.
Things are
worse than
they know.
Last
week, CMP
Assistant
Secretary
General
Michael
Adlerstein
belatedly told
member
states that
cost overruns
now are $265
million,
compared to a
previous
disclose of
less of $80
million,
supposedly
whittled down
through
something
called value
engineering.
But
even this
$265 million
overrun
understates
the problem,
as it does not
include
so-called
"associated
costs."
According to
the document
A/66/527/Add.1,
"the resources
required for
associated
costs for
the period
from 2008 to
2013 are
estimated to
total
$146,806,000."
So
the actual CMP
cost overrun
under Ban and
Adlerstein is
$412 million.
Recently there
was a push to
override local
opposition and
make plans to
build
another new UN
building,
tentatively
called DC-5,
on the
playground
to the south
of 42nd
Street, where
currently
children play
sports,
and adults
soccer in the
afternoon.
Now,
sources tell
Inner City
Press, the
idea of the UN
building yet
another
building
seems
"absurd," with
the over $400
million
overrun on a
mere
reconstruction.
Watch this
site.
(c) UN Photo
UN under
repair, $400M
& DC-5 not
shown
Footnote:
Inner
City Press alluded to
this coming
disclosure
last week,
even as
a major wire
service (mis)
reported that
the CMP cost
overrun was
"only" four
percent.
Meanwhile the
UN has refused
to answer
Inner City
Press'
repeated questions
about who is
getting paid
by the
UN to
accompany Kofi
Annan to Syria
-- TV images
show for
example
former UN
official Alan
Doss, who left
amid a
nepotism
scandal in
which he asked
UNDP to bend
or break its
rules to give
a job to his
daughter --
and about the
propriety
of the return
as a UN
adviser of
another former
official,
Maurice
Strong, who
left amid the
Oil for
Food scandal,
and another
bout of
nepotism.
Mismanagement
and
corruption may
be different
things -- but
lack of
transparency
in the
use of public
money fuels
both of them.
Watch this
site.
Update:
at the noon
briefing on
March 13, the
day after
Inner City
Press
published the
above, Inner
City Press
asked Ban
Ki-moon's
spokesman a
series of
questions. He
has now
emailed what
follows, first
to Inner City
Press then all
correspondents:
Subject:
Your
question on
the CMP
To:
Matthew.Lee[at]
innercitypress.com
From:
UN
Spokesperson -
Do Not Reply
[at] un.org
Date:
Tue,
Mar 13, 2012
at 1:30 PM
The
Fifth
Committee last
week has begun
to consider
the
Secretary-General's
9th annual
progress
report on the
implementation
of the Capital
Master Plan
(CMP) that had
been published
in October
2011.
On
8
March 2012 ASG
Adlerstein
informed the
Fifth
Committee that
the
projection of
the budget
shortfall
given in the
progress
report had
to be revised.
It is now
estimated to
be $265
million or
14.2 % over
budget.
The
CMP
in its
progress
reports has
been reporting
annually on
projected
budget
overruns since
its budget of
$1.876 billion
was approved
by
the General
Assembly in
December 2006.
In
September
2007 in its
5th annual
progress
report the CMP
reported a
projected
budget overrun
of $219
million,
approximately
12 %. This
was due to
inflation and
delays in the
execution of
the project.
As
the
project now
approaches its
final stages,
the recently
revised
projection is
due to many
factors,
including
numerous
unforeseen
conditions and
complexities
in the
basements,
where lack of
as-built
plans is
making
infrastructure
work very
intensive.
Also the
amount
of
asbestos-containing
material that
had to be
abated
exceeded the
initial
assumptions.
The
associated
costs ($146.8
million) are
temporary
costs of
certain
other
departments
incurred in
support of the
CMP, including
the costs
for new
furniture.
Those costs
were not part
of the CMP
budget,
although the
GA directed
the CMP to
cover and
absorb those
costs.
As
laid
out in its 9th
Annual
Progress
Report in
October 2011,
the CMP
is requesting
commitment
authority from
the Fifth
Committee to
utilize
interest
earned on the
Capital Master
Plan fund
($107
million) and
the CMP’s
Working
Capital Fund
($45 million)
to ensure
the project
can continue
to meet its
schedule.
To
complete
the project,
an additional
appropriation
will need to
be
discussed in
the fall
session of the
General
Assembly.